NCC won the construction work of Bangalore Metro Airport line

Loading...

NCC Limited today emerged as the lowest bidder for the construction of all 3 packages of the 37 km Airport Line (Blue Line) of Bangalore Metro, which will connect Kempegowda International Airport (KIA) in Bengaluru with KR Puram.

These 3 Elevated Packages Bangalore Metro Phase 2B The project ranges from 11 to 15 kilometers and includes 15 of the 17 planned stations on the line.

Bangalore Metro Rail Corporation Limited (BMRCL) has invited tenders With a time frame of 24 – 27 months for construction in July 2020. Technical bid was opened in June 2021 Reveal 5 Bidders A total of 12 bids were submitted.

Package 1

Financial bid price:

StrongDialect (Rs. in crore)
NCC739.04
SNC – CVCC JV753.86
afcon842.55
  • BMRCL Estimates: 639.95 crore
  • Closing period: 27 months
  • Length: 11.003 km
  • Tender: Phase 2B/P2/69(A)
  • Scope: Chainage Construction of elevated structures (viaducts and stations) of length 11.003 km (including 281.000 m viaduct beyond Phase 2A) from 0.000 m to 10072,000 m and eight elevated metro stations viz. Kasturi Nagar, Horamavu, HRBR Layout, Kalyan Nagar, HBR Layout, Nagawara, Veerannapalya and Kempapura, including 650.00 m link line connectivity to Baiyappanahalli, road widening, utility diversion and allied works of Bengaluru Metro Rail Project Phase-2B.

Package 2

Financial bid price:

StrongDialect (Rs. in crore)
NCC747.99
SNC – CVCC JV760.16
afcon811.16
GR Infra858.73
  • Assessment: 645.30 crore
  • Closing period: 24 months
  • Length: 11.678 km
  • Tender: Phase 2B/P2/69(B)
  • Scope: Chainage Construction of Elevated Structure (Viaduct and Station) of length 11.678 km from 10072.00 m to 21500.000 m and five elevated metro stations viz. Hebal, Kodigehalli, Jakkur Cross, Yelahanka and Bagalur Cross, consisting of 250 m pocket track, road widening, utility diversion and allied works of Bengaluru Metro Rail Project Phase-IIB.

Package 3

Financial bid price:

StrongDialect (Rs. in crore)
NCC680.21
SNC – CVCC JV692.27
afcon809.11
GR Infra826.93
ITD KEMdisqualified
  • Assessment: 620.88 crore
  • Closing period: 24 months
  • Length: 15.011 km
  • Tender: Phase 2B/P2/69(C)
  • Scope: Chainage Construction of elevated structure (viaduct and station) of length 15.011 km from 21500.000m to 36511.000m and two elevated metro stations. Bettahalasuru and Doddajala, including road widening utility diversion and allied works of Bengaluru Metro Rail Project Phase-IIB. This length includes about 718.18 meters cut and covered portion in front of Yelahanka Air Force Station.
BangaloreMetroAirportMap2020 Kolkata Metro
Bangalore Metro’s Airport Line route marked with major stations 

I’m surprised ITD has been disqualified. NCC’s bid was still 15.46%, 15.91% and 9.55% higher than BMRCL’s estimate for each package, which makes award of contracts difficult, especially for packages 1 and 2 which cities are close to.

BMRCL will certainly invite the management of NCC for talks in the coming weeks and I look forward to seeing the outcome. I don’t see this title in a time consuming retainer, but you never know.

NCC’s prior experience in Bengaluru includes construction of the second phase extension of the 5.799 km Yelachenahalli-Silk Institute of Green Line which opened in January 2021 to engage in some minor civil work Anjanapura Depot still going on.

Coming back to Phase 2B, tender notices for the following packages are still pending:

  1. Doddajala Depot (“Airport Depot”) at Trumpet Interchange
  2. Expansion of Baiyapanahalli Depot
  3. Construction of Sky Garden and KIA Terminal Stations (from BIAL)

1 and 2 can be combined into one civilian package as they would have 1 Detailed Design Consultant.

For more updates, see Bangalore Metro Section