4 bidders for DC-05 underground work of Delhi Metro Phase 4

Loading...

After the Delhi Metro Rail Corporation (DMRC) opened the technical bids today, 4 construction firms have submitted bids for construction of tunneling contract DC05 of Delhi Metro of 28.92 km Janakpuri West-RK Ashram extension of Magenta Line.

This underground section of 7.46 km is north of Derawal Nagar with RK Ashram via 6 stations Derawal Nagar, Ghanta Ghar, Pulbangash (interchange with Red Line), Sadar Bazar, Nabi Karim and Ramakrishna Ashram Marg (interchange with Blue Line). ) adds.

Loading...

It is 65.1 km. It features the Magenta Line’s fourth (and final) Citizen package. Phase 4 Project. Other packages 12.375 kms. Huh DC-01, 7.473 km DC-03R, 2.03 km Underground DC-06 – All are under construction.

DMRC invited tenders For this contract – Funded by JICA Through a loan of Rs 8,390 crore – in June 2021 with a 42-month deadline and an undisclosed estimate. He had earlier estimated that it would cost Rs. 2444.828 crores, but I am not sure if it is still operational.

Loading...

Bidders:

  • afcons infrastructure
  • Gulermak Agir Sanay Insat Ve Tahut Aas
  • ITD Cementation (ITD Cement)
  • Larsen & Toubro (L&T)

Short range: Design and Construction of Twin Tunnel by Shield TBM, Tunnel by Cut and Cover, Underground Ramp at Derawal Nagar and Six Underground Stations viz. Derawal Nagar, Ghanta Ghar, Pulbangash, Sadar Bazar, Nabi Karim and Ramakrishna Ashram Marg including Architectural Finishing, Water Supply, Sanitary Installation, Drainage works of Stations of Phase-IV of Janakpuri West to RK Ashram Corridor (Line-8 Extension) . Delhi MRTS.

Loading...
DelhiMetroDC05Map Kolkata Metro
Alignment of Package DC-05 of Delhi Metro Magenta Line – Step 4 View Route Map with exact locations of all stations

The bids have now been sent for technical bid evaluation which may take a few months to complete. When this is done, the financial bids of the technically qualified bidders will be opened to identify who is the lowest bidder and most likely contractor.

The assigned contractor will have to use at least 4 Tunnel Boring Machines (TBMs). The DC-05’s design details such as crossover and ramp locations can be seen here.

Loading...

DMRC has publicly posted that they are pursuing the June 2024 deadline to start operations on the 28.92 km extension of the Magenta Line between Janakpuri West – RK Ashram. This construction will not be possible due to practicalities and I think this section is not opening before mid 2026 at this time.

With this development, technical bids have been opened for all 4 JICA-funded underground packages of Phase 4. I believe that by the end of the year, if possible, we will start opening financial bids in November with the award of construction contracts.